Civil Engineering Project:
Technip Deephaven Spool Base 2007
HQC won the stalk racks and bases contract after completing a new car park contract for the base.
The contract, which lasted approximately six months and involved the construction of 192 no 12m long * 1m wide bases for the two new rack systems that were put in place taking 1730 metres cubed of concrete .
Earth works included the excavation of 14000 cubic metres of existing material and then importing new aggregate to construct two no new 10m wide road ways. HQC carried out these works mostly self supervised.
|